DC/26/01413ApproveDecision issued 12 May 2026
Application to amend working hours for the Progress Power Gas Fired Power Station to include weekends (07:00 - 19:00) from May 1, 2026, to April 30, 2027.
Proposal as recorded
The Progress Power (Gas Fired Power Station) Order 2015: Application pursuant to requirement 16(2) to amend working hours to include Saturday - Sunday (07:00 - 19:00) from 01st May 2026 to 30th April 2027 (Weekend extended hours)
Record details
AddressNational Grid Yaxley 400kV Substation Leys Lane Yaxley Eye Suffolk IP23 8DX
Application typeDischarge of Requirement
StatusDecided
DecisionApprove
Decision levelN/A
Received26/03/2026
Validated01/04/2026
Decision issued12/05/2026
WardPalgrave
ParishYaxley
Parties as recorded
ApplicantSign in to view
Applicant companyN/A
AgentN/A
Agent companyN/A
Case officerGemma Walker