DC/26/2268/CONUnknownLast updated 25/07/2026, 23:51

Consultation regarding the construction, operation, maintenance, and decommissioning of a ground-mounted solar park with a capacity exceeding 100MW.

The development includes underground cabling connecting the facility to the Yaxley Substation.

Other Consultation

Get notified about the decision

Sign in and like this application to get an email when the decision is made.

Full Proposal

Consultation - The Project comprises the construction, operation, maintenancedecommissioning of a ground mounted solar park with a generating capacity of more than 100MW (megawatts) of alternating current (AC) capacity. The Project will connect to the National Grid via underground cabling to the Yaxley Substation.

Application Timeline

Application Registered22/06/2026
Application Validated22/06/2026
Decision MadeN/A