Skip to content
DC/26/1958/DRRApproveLast updated 01/08/2026, 21:20

Approval of details relating to the use of tower cranes during the construction phase of the substation.

Discharge of Requirements (56 days)

Keep track of this application

Sign in and like this application to get an email when the decision is made.

Full Proposal

Discharge of Requirement 40 (Amendments to approved details - Use of Tower Cranes during the Construction of Kiln Lane Substation) Substation Stage of East Anglia ONE North Offshore Wind Farm Development Consent Order

Application Timeline

Application Registered27/05/2026
Application Validated27/05/2026
Decision MadeN/A
Decision Issued29/07/2026