26/00598/CONDCDecidedLast updated 24/07/2026, 12:44
Approval of details is sought for conditions 8 and 13 relating to a construction environmental management plan and biodiversity net gain implementation.
The details pertain to a previously approved low-carbon hydrogen production facility.
Condition Clearance
Essex, UK
Get notified about the decision
Sign in and like this application to get an email when the decision is made.
Full Proposal
Application for the approval of details reserved by condition Nos. 8 (Construction Environmental Management Plan - CEMP) & 13 (Biodiversity Net Gain Implementation) of planning permission ref: 25/00918/FUL (Construction and operation of an electrolytic low carbon hydrogen production site, comprising electrolysers, an electrical switchroom, compressors, tube trailer filling bays, medium pressure storage tanks, buffer storage tanks and associated hard and soft landscaping.)
Application Timeline
Application Registered29/05/2026
Application Validated03/06/2026
Decision MadeN/A
Decision Issued03/07/2026
Approximate area shownSign in for the exact location
Case Officer
Applicant