26/42346/NOTHApproveLast updated 23/07/2026, 11:17

Replacement of 140 metres of overhead open wire conductor with bunched conductor and upgrading of a single pole transformer structure to an H-pole.

Other Notifications
Outwoods, Newport, UK

Keep track of this application

Sign in and like this application to get an email when the decision is made.

Full Proposal

Replace 4 spans of open wire conductor with bunched ABC conductor totalling 140m. Upgrading existing single pole mounted transformer pole and two stay wires 85GNDEA9 to a 'H' pole

Application Timeline

Application Registered08/06/2026
Application Validated08/06/2026
Decision Made10/07/2026
Decision Issued10/07/2026
Approximate area shownSign in for the exact location

For neighbours

Physical construction works
Build-phase noise, dust and vehicles while works are carried out.