Skip to content
PA/2026/0409Approve With ConditionsLast updated 25/07/2026, 04:58

Fire safety remediation works are proposed for the Quartz and Graphite Buildings in Salford.

The project involves replacing the ground-floor outer brickwork and combustible insulation with non-combustible alternatives, as well as replacing timber balcony decking with non-combustible flooring.

Full planning permission
Stanley Street, Salford M3

Keep track of this application

Sign in and like this application to get an email when the decision is made.

Full Proposal

Removal of the ground floor facing brickwork outer skin to allow removal of combustible insulation and installation of new cavity barriers, non-combustible insulation, and a new facing brickwork outer skin. Removal of existing timber decking to recessed and projecting balconies, with installation of new non-combustible balcony decking.

Application Timeline

Application RegisteredN/A
Application Validated17/03/2026
Decision MadeN/A
Decision Issued13/07/2026
Approximate area shownSign in for the exact location

For neighbours

Physical construction works
Build-phase noise, dust and vehicles while works are carried out.
Upper-floor or window works
First-floor, dormer, balcony or window works in the description.

What the application involves, identified from its description — an indicator, not an assessment. Set your address to see distance and direction.

Agent

Stephen Bold

More Information