An outline planning application has been submitted for a large data centre facility with a gross internal area of up to 356,500 square metres.
The scheme includes ancillary offices, substations, power plant, emergency generators, and associated site infrastructure, landscaping, engineering and drainage works.
Get notified about the decision
Sign in and like this application to get an email when the decision is made.
Full Proposal
Consultation on outline planning permission, with all matters reserved except access (26/02160/OUTES) for a Data Centre facility (Use Class B8) totalling up to 356,500sqm gross internal area with ancillary power generation (up to 49.9MW), including Data Centre buildings, ancillary offices, substations, power plant, emergency generators, and associated site infrastructure, landscape, engineering and drainage works
Application Timeline
For neighbours
What the application involves, identified from its description — an indicator, not an assessment. Set your address to see distance and direction.