25/07/EIASCRApproveDecision issued 27 Feb 2026

Request for an Environmental Impact Assessment Screening Opinion for installing a 9.4km underground water pipeline.

Proposal as recorded

Environmental Impact Assessment Screening Opinion for the installation of a 9.4km below-ground water pipeline

Record details

AddressHallgates To Elms Farm Pipeline
Application typeEIA Screening Opinion
StatusDecided
DecisionApprove
Decision levelDelegated
Received26/09/2025
Validated26/09/2025
Decision issued27/02/2026
WardGlenfield Ellis
ParishGlenfield Parish Council
View on the council's portal

Parties as recorded

ApplicantN/A
Applicant companySevern Trent Water
AgentN/A
Agent companyFisher German
Case officerStephen Dukes

Location

Hallgates To Elms Farm Pipeline