This is an archived application
A snapshot from the original Planatom register, last updated 20 November 2025. It is not kept up to date — for what's happening now, use the current register.
71888Approve With ConditionsDecision issued 20 Nov 2025
Application to construct, operate, and decommission a Battery Energy Storage System (BESS) facility with related infrastructure.
Proposal as recorded
Construction, operation and decommissioning of a Battery Energy Storage System (BESS) facility and associated infrastructure
Record details
AddressShore Top Farm, Kearsley Road, Radcliffe, Manchester, M26 1FA
Application typeFull
StatusDecided
DecisionApprove With Conditions
Decision levelDelegated
Received28/04/2025
Validated22/05/2025
Decision issued20/11/2025
WardRadcliffe - West
ParishN/A
Parties as recorded
ApplicantN/A
Applicant companyTaiyo Power & Storage
AgentMiss Maureen Maureen Darrie
Agent companyGP Planning
Case officerJennie Townsend