DC/094002ApproveDecision issued 24 Jul 2025

Application to install a 75MW Battery Energy Storage System (BESS) with related equipment and infrastructure.

Proposal as recorded

Installation of a 75MW Battery Energy Storage System (BESS) together with associated equipment and infrastructure.

Record details

AddressLand Off Ashton Road Bredbury Stockport SK6 2QE
Application typeFull Application
StatusDecided
DecisionApprove
Decision levelN/A
Received08/11/2024
Validated06/01/2025
Decision issued24/07/2025
WardBredbury & Woodley (Wern)
ParishN/A
View on the council's portal

Parties as recorded

Applicant companyN/A
AgentN/A
Agent companyPegasus Group
Case officerMr Dave Westhead

Location

Land Off Ashton Road Bredbury Stockport SK6 2QE

Open in maps