24/02291/FULApproveDecision issued 5 Mar 2026

Application to extend the existing SPEN 132kV Substation, build a new access road, and install security fencing.

Proposal as recorded

Extension of existing SPEN 132kV Substation and provision of a new access road and security fencing

Record details

AddressSouth Site Stanlow Refinery Oil Sites Road Ellesmere Port CH65 4EN
Application typeFull Application
StatusDecided
DecisionApprove
Decision levelN/A
Received05/08/2024
Validated28/08/2024
Decision issued05/03/2026
WardGowy Rural
ParishThornton Le Moors
View on the council's portal

Parties as recorded

Applicant companyN/A
AgentMrs Helen Johnson
Agent companyN/A
Case officerSteven Holmes

Location

South Site Stanlow Refinery Oil Sites Road Ellesmere Port CH65 4EN