24/01681/PPPending
Application to extend the operational lifespan of 46 wind turbines and associated infrastructure by 6 years to 2034, under Section 42 to vary Condition 2 of Planning Permission 98/00597/DET.
Proposal as recorded
Application under Section 42 to Vary Condition 2 of Planning Permission 98/00597/DET (Erection of 46 wind turbines and associated infrastructure) - to extend the operational lifespan for an additional 6 years to 2034
Record details
AddressBeinn An Tuirc Windfarm Bellochantuy Campbeltown Argyll And Bute
Application typePlanning Permission
StatusPending
DecisionN/A
Decision levelN/A
Received11/09/2024
Validated16/09/2024
Decision issuedN/A
WardKintyre And The Islands
ParishN/A
Parties as recorded
ApplicantN/A
Applicant companyScottish Power Renewables
AgentN/A
Agent companyITPEnergised
Case officerStuart Ramsay