24/03468/P14ApproveDecision issued 8 Jan 2025

Installation of a 75 kWp solar photovoltaic system on an existing building roof, with an estimated annual generation of 60,406 kWh. The project is funded by the Rural Payment Agency's Farming Investment Fund and Improving Farm Productivity grant.

Proposal as recorded

Installation of a solar photovoltaic system with supporting hardware on an existing building roof. The system capacity is 75 kWp with an estimated annual generation of 60,406 kWh. The farm has been accepted for grant funding from the Rural Payment Agency (RPA) - Farming Investment Fund and Improving Farm Productivity grant (RPA Project reference: S-90A-ESC).

Record details

AddressOld Hall Farm Stretton Hall Lane Stretton Malpas SY14 7JE
Application typeSolar equip on non-domestic premises
StatusDecided
DecisionApprove
Decision levelN/A
Received19/11/2024
Validated19/11/2024
Decision issued08/01/2025
WardFarndon
ParishTilston
View on the council's portal

Parties as recorded

Applicant companyN/A
AgentMr Tim Davies
Agent companyN/A
Case officerEdward Bannister

Location

Old Hall Farm Stretton Hall Lane Stretton Malpas SY14 7JE