DC/26/00551/OHLDecidedLast updated 20/08/2026, 21:00
The proposal involves replacing existing utility poles with new wooden and steel poles, adding a stay wire, and upgrading the line to an aerial bundled conductor.
Overhead Electricity Lines
Gateshead Road, Newcastle upon Tyne
Get notified about the decision
Sign in and like this application to get an email when the decision is made.
Full Proposal
Replace two existing poles with two new wooden poles, including the installation of one stay wire, replace an additional pole with a steel pole, and upgrade the existing line to Aerial Bundled Conductor (ABC)
Application Timeline
Application Registered07/07/2026
Application Validated07/07/2026
Decision MadeN/A
Decision Issued18/08/2026
Approximate area shownSign in for the exact location
Case Officer
Applicant
Northern Powergrid (Northeast) PLC