DC/26/2886/CONPendingLast updated 15/08/2026, 20:44

Upgrade of the existing pole mounted transformer to 50kVa to facilitate a new connection.

Other Consultation
Silverlace Green, Benhall, Saxmundham IP17, UK

Get notified about the decision

Sign in and like this application to get an email when the decision is made.

Full Proposal

Consultation - To facilitate a new connection it has become necessary for Eastern Power Networks plc to upgrade the existing pole mounted transformer to 50kVa.

Application Timeline

Application Registered13/08/2026
Application Validated13/08/2026
Decision MadeN/A
Decision IssuedN/A
Approximate area shownSign in for the exact location

For neighbours

Physical construction works
Build-phase noise, dust and vehicles while works are carried out.

What the application involves, identified from its description — an indicator, not an assessment. Set your address to see distance and direction.

Case Officer