DC/26/03280ApproveLast updated 08/08/2026, 17:18

Proposals involve upgrading the existing high voltage overhead line to three phase.

Development by statutory undertaker
Burstall, SK S0N 0H0, Canada

Keep track of this application

Sign in and like this application to get an email when the decision is made.

Full Proposal

Development by a Statutory Undertaker - upgrading the existing high voltage overhead line to three phase.

Application Timeline

Application Registered29/07/2026
Application Validated31/07/2026
Decision Made05/08/2026
Decision Issued05/08/2026
Approximate area shownSign in for the exact location

For neighbours

Physical construction works
Build-phase noise, dust and vehicles while works are carried out.

What the application involves, identified from its description — an indicator, not an assessment. Set your address to see distance and direction.

Case Officer

Applicant

Sign in to view name
Power Networks (UKPN).