26/01205/SCREENUnknownLast updated 22/07/2026, 08:48
A screening opinion is sought to determine whether an environmental impact assessment is required to extend the time limit on planning permission 22/01380/PP from three to ten years, allowing for completion of grid connection works for a wind farm.
Screening Opinion
Kilmartin, Lochgilphead, UK
Get notified about the decision
Sign in and like this application to get an email when the decision is made.
Full Proposal
Screening Opinion for Application under Section 42 of the Town and Country Planning (Scotland) Act 1997 to vary the Standard Time Condition Limit of application reference 22/01380/PP from three years to ten years to allow for completion of grid connection works to connect the wind farm
Application Timeline
Application Registered13/07/2026
Application Validated13/07/2026
Decision Made14/07/2026
Decision Issued14/07/2026
Approximate area shownSign in for the exact location
Case Officer
Applicant
Sign in to view name
applicant_company_name